Ironwood School District


650 E Ayer St • Ironwood, MI 49938


Roofing Project Details

We are proud to have completed the Ironwood School District roofing project in Ironwood.

Type: Flat Roof

In 2009 and 2010 Nasi Roofing re-roofed L.L. Wright High School and Sleight Elementary School during two projects. The District re-roof project in 2009 and the High School addition in 2010 used the Duro-Last Roofing System and totaled approximately 104,000 square feet. The new custom prefabricated Duro-Last Roofing System was installed over 3" insulation. All pipes, chimneys, vents, and wall flashing were pre-measured and ordered to fit. This reduced the amount of field seams that had to be done, allowing the roof to be installed quickly and also maintaining a high level of quality. Upon completion a 20 year NDL Manufacturers Material & Labor Warranty was provided.